Independent Cost Estimate (ICE)

For all purchases above the Micro Purchase threshold, the PHA shall prepare an ICE prior to solicitation. The level of detail shall be commensurate with the cost and complexity of the item to be purchased.

Cost and Price Analysis

Ripley Housing Authority shall require assurance that, before entering into a contract, the price is reasonable, in accordance with the following instructions.

Petty Cash and Micro Purchases

No formal cost or price analysis is required. Rather, the execution of a contract by the contracting officer (through a purchase order or other means) shall serve as the contracting officer's determination that the price obtained is reasonable, which may be based on the contracting officer's prior experience or other factors.

Small Purchases

A comparison with other offers shall generally be sufficient determination of the reasonableness of price and no further analysis is required. If a reasonable number of quotes is not obtained to establish reasonableness through price competition, the contracting officer shall document price reasonableness through other means, such as prior purchases of this nature, catalog prices, the contracting officer's personal knowledge at the time of purchase, comparison to the ICE, or any other reasonable basis.

Sealed Bids

The presence of adequate competition should generally be sufficient to establish price reasonableness. Where sufficient bids are not received and when the bid received is substantially more than the ICE, and where Ripley Housing Authority cannot reasonably determine price reasonableness, the PHA must conduct a cost analysis, consistent with federal guidelines, to ensure that the price paid is reasonable.

Competitive Proposals

The presence of adequate competition should generally be sufficient to establish price reasonableness. Where sufficient bids are not received, Ripley Housing Authority must compare the price with the ICE. For competitive proposals where prices cannot be easily compared among offerors, where there is not adequate competition, or where the price is substantially greater than the ICE, the PHA must conduct a cost analysis, consistent with federal guidelines, to ensure that the price paid is reasonable.

Contract Modifications

A cost analysis, consistent with federal guidelines, shall be conducted for all contract modifications for projects that were procured through sealed bids, competitive proposals, or non-competitive proposals, or for projects originally procured through small purchase procedures and the amount of the contract modification will result in a total contract price in excess of $100,000.